Building 1: from drawings to material choices
Room-by-room material specifications are being prepared for Building 1, including proposed floors, colours, doors and windows. Some choices remain under review.
Read note
RUMAH KAMBERA · CONSTRUCTION JOURNAL
Short, dated updates from the construction of our future socio-medical community centre in Kawangu, East Sumba. Each entry records a concrete step, document or decision.
Room-by-room material specifications are being prepared for Building 1, including proposed floors, colours, doors and windows. Some choices remain under review.
Read note3 October 2026: Workers were completing the final side of the Rumah Kambera boundary wall, before the planned levelling of the northeast section.
Read note25 September 2026: Electricity was connected to Rumah Kambera, supporting basic site work and providing evening light in the wooden lopo.
Read note19 September 2026: Two contributions totalling CHF 19,000 helped move site work forward, with much of the centre still unfunded at that date.
Read note26 August 2026: The Kawangu site survey mapped elevations, contours and drainage, providing measured information for the next construction phase.
Read note10 May 2026: The first deep drilling at Rumah Kambera found water after two days of work, an essential step before preparing the permanent centre in Kawangu.